Hollywood Seawall Raise Deadline: Citations, 2035 and the 2034 Review

Hollywood has no citywide date by which existing seawalls must be raised. Two things set deadlines: a citation, which gives you 60 days after the citation to show progress and 365 days to complete repairs, and the January 1, 2035 cutoff for permitting a new or substantially repaired wall at 4 feet instead of 5 (Sec. 150.30).

Updated October 26, 2026 · Sources linked throughout and listed below · General information, not legal or engineering advice

What gets a Hollywood seawall cited

Section 150.30 presumes a barrier is in disrepair if tidal surface water flows through or over it onto a neighbor's property or the public right-of-way, and failing to keep a barrier in good repair is a citable offense (Sec. 150.30). Age alone is not the trigger. Water crossing your property line is.

How the 365 days really works

If the repair that stops the water is small, 365 days is usually comfortable. If it counts as a substantial repair, the code requires the wall to be designed, permitted, built and pass final inspection at the required elevation within those same 365 days. That year has to absorb a survey, engineering, the city building permit and the Broward County Environmental Resource General License, and possibly Florida DEP, South Florida Water Management District or Army Corps review (city checklist).

The 2035 and 2050 dates

  • Before January 1, 2035: an application for a new or substantially repaired barrier can be permitted at 4 feet NAVD88 if it is designed and built to accommodate 5 feet.
  • By January 1, 2050: a wall permitted at 4 feet must be able to reach 5 feet.
  • In 2034 or before: the city will re-evaluate the 5 foot requirement using updated sea level rise projections (Sec. 150.30).

If you expect to rebuild in the next decade, the practical question is whether to build to 5 feet now or to 4 feet with a design that can be raised. Pricing both is worth it.

A realistic first 60 days after a Hollywood citation

  1. Note the citation date. Both deadlines run from it.
  2. Photograph the overtopping or leak at high tide, with the date.
  3. Have a licensed contractor or engineer inspect the wall and say whether the fix is a targeted repair or a substantial repair.
  4. Order a survey in feet NAVD88 if a rebuild is likely.
  5. Keep records of every step, and call the city before a deadline if the schedule slips.

More detail is in what to do after a seawall citation. For the elevation rule, see the Hollywood seawall height requirement.

Planning seawall work in Hollywood?

Call (754) 484-1777 or request a free quote at ftlseawallrepair.com. We connect Hollywood waterfront owners with licensed, insured local seawall contractors who handle the engineering, permits and inspections. We do not perform the work ourselves.

Call (754) 484-1777

Hollywood seawall questions

How long do I have after a seawall citation in Hollywood?

Section 150.30 gives the owner 60 days after the citation to show progress and 365 days to complete repairs. A substantial repair must be designed, permitted, built and pass final inspection within those 365 days.

Do I have to raise my Hollywood seawall by 2035?

No. January 1, 2035 is the cutoff for permitting a new or substantially repaired wall at 4 feet NAVD88 instead of 5. It is not a deadline for every existing wall.

If I apply in 2034, can I still build my Hollywood seawall at 4 feet?

Under the current code, an application submitted before January 1, 2035 may be permitted at 4 feet NAVD88 if the wall is designed to reach 5 feet by 2050. Because the city plans to re-evaluate the standard in 2034, confirm with the Building Division first.